Dong Dok Castle.
Cameron & Sunny Stovold's Residence
The project, in brief.
What's on file so far.
Every number below counts real, vetted files already in your project folder, not an estimate.
Mobilization contract.
The mobilization advance was received on 9 Jul 2026 — thank you — and the agreement was signed on 14 Jul 2026; the team can now mobilise on your land. Meanwhile the work continues: the 3D visualisation of your house is in production, the Bill of Quantities is being calculated, and permits and the construction schedule are in planning.
- Site clearing and leveling
- The access track
- Power and water to site
- The surveyor's pegs
- The permit application
- Team mobilized on your land
- In Production
- In Progress
- In Planning
- In Motion
- Signed
- Later
Delivered Mon 6 Jul, 7:09 PM
- UpdatePortal refreshed. Awaiting the BOQ, the final plan PDF and the first 3D visualisations; all three land here as soon as they are ready.Fri 24 Jul
- BOQBOQ with the Lao engineer for sign-off. The team is pushing to complete it as quickly as possible.Thu 23 Jul
- BankLand title timing noted. The developer quotes about 2 months; the team will coordinate with the developer’s office and support your bank’s requirements.Thu 23 Jul
- SignedMobilisation agreement e-signed. The executed copy is on your Documents page.Tue 14 Jul
- 3D3D visualisation started. The complete house is in production with the visual team; first images will appear on the Design page.Tue 14 Jul
- Round 4Your final review notes received. Notes on the Round 4 set returned and now with the design team.Tue 7 Jul, 12:00 PM
- Round 4Full drawing set delivered, four sheets. Your review notes received.Mon 6 Jul, 7:09 PM
- DesignIsland enlarged for the wine cooler. About 20 cm larger, power inside the island; drawn into the set the same day.Mon 6 Jul, 12:14 PM
- Round 4Kitchen island arrangement drawn. Checked against the brief.Sat 4 Jul, 5:02 PM
- Round 3Fully dimensioned drawing set delivered. Thirteen sketch iterations approved.Thu 3 Jul, 3:35 PM
- ConceptConcept locked: A, Bright White Classical, on the Option 2 plan.Mon 22 Jun
- Round 2Two design options presented.Sun 21 Jun
- Round 1First concept drawings delivered.Mon 15 Jun
- SiteD2 walked with Cameron and Sunny.Thu 21 May
- PaymentDesign fee received in full, USD 3,000.Tue 12 May
- AgreementDesign contract e-signed, Ref. MLH.DSN.2026.002.Tue 12 May
- ProposalProposal for Dong Dok Castle accepted.May 2026
Everything your build will need.
The portal grows with the project. What is live today is open; the rest switches on the day construction starts.
Design
Every round, every change, every sheet, and the concept gallery.
OpenAgreement
The mobilization contract. Read it in full before you sign.
OpenPayment
Design fee, the mobilization advance, and the draw schedule ahead.
OpenBrief
The plot, the programme, the direction. Schedule B in full.
OpenDocuments
Proposal, contract, signed agreement, and every drawing set.
OpenMessages
The important messages with the team, kept in one place.
OpenAppointments
Book a call or a site visit with the team.
OpenBuild Timeline
The draw schedule ahead, phase by phase, from mobilization to handover.
OpenQuestions? A short call beats a long email.
- Emailclients [at] modernlaohomes.com
- WhatsAppWhatsApp the team
- Book a timeAppointments, calls and site visits
Drawings, the agreement, a payment reference: message us live on WhatsApp or book a call.
Replies within working hours (ICT). Off-hours messages are answered first thing.