Weekly Progress Report · Sample

What you will receive every Wednesday.

A real example of the weekly progress report each Modern Lao Homes client receives during construction. Names and figures below are illustrative.

modernlaohomes.com
A sample for review only
Project · Sample Residence
Weekly Progress Report

Week 18 · 22 October 2026

Roof framing complete · Window installation begins next week

ProjectMLH-CON-2026-014
SiteBan Phonsaat, Vientiane
PhaseConstruction · 7 of 12
AuthorMr. Ping (Site Engineer)
Reviewed byAdrian Holcombe
This week, in one paragraph
Roof framing was completed on Tuesday, two days ahead of schedule, after favourable weather over the weekend. The roof tile delivery arrived Thursday morning and is staged on site. We have begun preparation for window installation, scheduled for Monday — please confirm by Friday whether you are proceeding with the upgraded double-glazing on the western elevation (an optional variation) so we can release the supplier order on Saturday.
42%
Construction
Progress
+2
Days ahead
of schedule
14
Site days
this period
0
Safety
incidents
02
Week 18 · Continued

Completed this week

  • Roof framing · all four elevations · structural sign-off Tue 14:30
  • Roof tile delivery received and staged (3,200 tiles, Lampang)
  • First-floor electrical first fix · 80% complete (residual outlets pending)
  • Plumbing rough-in · ground floor bathrooms pressure-tested
  • Site drainage trenching complete · gravel backfill scheduled Mon
  • Variation MLH-VAR-017 (added external tap, garage) installed

Scheduled next week

  • Window installation · western and southern elevations
  • Roof tile installation · subject to weather
  • First-floor electrical second fix · light fittings pending arrival
  • Site drainage gravel backfill (Monday)
  • Plasterboard delivery · Wednesday (already paid)
  • Tile sample selection meeting · in portal Friday

Items requiring your attention

03
Photograph · Week 18

Roof framing, complete.

Roof framing complete on the western elevation, before tile delivery
Western elevation, looking south · Tuesday afternoon, before tile delivery

Notes from the site

The framing carpenter, Mr. Bounthanh, has been with us on eleven projects. The tolerances on this roof are tighter than standard — we set them at ±3mm rather than the ±10mm typical for residential work — because the upgrade glazing on the western face requires it.

Six more photos in the portal

Site photos from this week — including the drainage trench, electrical first fix detail, and a wide-angle of the rear elevation — are uploaded to the project portal under Photos · Week 18. Click through whenever you have a moment.

04
Financial · Transparent

Payment status, this week.

No payment is due this week. The next milestone payment will be triggered by completion of window installation and roof tiling, expected in approximately three weeks.

Milestone Due Status Amount
05 · Roof & envelope complete ~ 12 Nov 2026 Approx 3 weeks USD 27,750
06 · MEP rough-in complete ~ 22 Dec 2026 Pending USD 27,750
07 · Practical completion ~ 28 Feb 2027 Pending USD 18,500
08 · Handover & retention release ~ 15 Mar 2028 12-month warranty period USD 9,250
USD 101,750
Paid
to date
USD 83,250
Remaining
(incl. variations)
USD 185,000
Contract
total
+1,840
Approved
variations
05
Snags & close

Open items & signoff.

Snag list (open)

Snag list (closed this week)

Mr. Ping
Site Engineer · Author

Available on site Monday through Saturday, 07:30–17:00. WhatsApp +856 20 5586 4422 for urgent items only — for non-urgent, please use the portal.

Adrian Holcombe
Head Engineer · Reviewed

I have reviewed this report and the underlying photos. The roof framing tolerance achieved meets the standard required for the upgrade glazing scheduled next week.

Next report: Wednesday 29 October 2026.