A real example of the weekly progress report each Modern Lao Homes client receives during construction. Names and figures below are illustrative.
Roof framing complete · Window installation begins next week
The framing carpenter, Mr. Bounthanh, has been with us on eleven projects. The tolerances on this roof are tighter than standard — we set them at ±3mm rather than the ±10mm typical for residential work — because the upgrade glazing on the western face requires it.
Site photos from this week — including the drainage trench, electrical first fix detail, and a wide-angle of the rear elevation — are uploaded to the project portal under Photos · Week 18. Click through whenever you have a moment.
No payment is due this week. The next milestone payment will be triggered by completion of window installation and roof tiling, expected in approximately three weeks.
| Milestone | Due | Status | Amount |
|---|---|---|---|
| 01 · Mobilisation (10%) | 15 May 2026 | ✓ Paid 14 May | USD 18,500 |
| 02 · Foundation complete | 10 Jun 2026 | ✓ Paid 11 Jun | USD 27,750 |
| 03 · Ground floor structure | 22 Jul 2026 | ✓ Paid 23 Jul | USD 27,750 |
| 04 · First floor structure | 10 Sep 2026 | ✓ Paid 12 Sep | USD 27,750 |
| 05 · Roof & envelope complete | ~ 12 Nov 2026 | Approx 3 weeks | USD 27,750 |
| 06 · MEP rough-in complete | ~ 22 Dec 2026 | Pending | USD 27,750 |
| 07 · Practical completion | ~ 28 Feb 2027 | Pending | USD 18,500 |
| 08 · Handover & retention release | ~ 15 Mar 2028 | 12-month warranty period | USD 9,250 |
Available on site Monday through Saturday, 07:30–17:00. WhatsApp +856 20 5586 4422 for urgent items only — for non-urgent, please use the portal.
I have reviewed this report and the underlying photos. The roof framing tolerance achieved meets the standard required for the upgrade glazing scheduled next week.
Next report: Wednesday 29 October 2026.
Every Wednesday during construction. By email, in the portal, and (if you ask for it) by WhatsApp. The same level of detail. Every week. From day one to handover.